AGENDA MEMORANDUM
Meeting Date: June 22, 2009
From: Raymond S. Sharp, Environmental Services/Public Works Director
Subject: Resolution authorizing execution of a Change Order for Construction Management Services, Operations and Maintenance Manual Update and Ground Water Monitoring Plan for work associated with upgrades to the Turnpike Water Reclamation Facility
Staff Recommendation:
Staff recommends approval of the Change Order to AECOM USA, Inc. in the amount of $179,501.00, with funding provided from the 2007 bond issue and from Water Protection and Sustainability Program grant funding.
Analysis:
During the meeting of May 26, 2009, the City Commission awarded a construction contract to TLC Diversified for the construction of upgrades to the Turnpike Water Reclamation Facility. This authorization is for AECOM USA, Inc. Successor in Interest to Boyle Engineering Corporation to provide necessary construction management services, permit-required operation and maintenance manual updates and permit-required ground water monitoring plan.
Funding for these services will primarily be drawn from the 2007 bond issue proceeds. A portion of these services are eligible for reimbursement from the St. Johns River Water Management District-administered Water Protection and Sustainability Program grant which the City received several years ago.
Options:
1. Approve the Change Order as presented; or,
2. Such alternative action as the Commission may deem appropriate
Fiscal Impact:
There are ample funds available for this purpose from the 2007 bond fund proceeds. Of the total Change Order amount of $179,501.00, approximately $110,000.00 is eligible for 20% reimbursement; therefore, the city will receive approximately $22,077.00 in reimbursed costs from the Water Protection and Sustainability Program grant.
|
Department: Environmental Services Prepared by: R. Sharp Attachments: Yes X No ______ Advertised: ____Not Required X Dates: __________________________ Attorney Review : Yes___ No X
_________________________________ Revised 6/10/04 |
Reviewed by: Dept. Head rss
Finance Dept. _______JB_________
Deputy C.M. ___________________ Submitted by: City Manager ___________________ |
Account No. 043-3099-533-6310
Project No. 430007__________
WF No. 506969-001__________
Budget ___ $179,501_________
Available $179,501________ |
RESOLUTION NO._______________
A resolution of the City Commission of the City of Leesburg, Florida, authorizing the Mayor and City Clerk to execute Change Order No. 1 to Task Order No. 27 with AECOM USA Inc., Successor in Interest to Boyle Engineering Corporation for construction management services, operation and maintenance manual update and ground water monitoring plan for the Turnpike Water Reclamation Facility; and providing an effective date.
BE IT RESOLVED BY THE CITY COMMISSION OF THE CITY OF LEESBURG, FLORIDA:
THAT the Mayor and City Clerk are hereby authorized to execute an agreement with AECOM USA, Inc. Successor in Interest to Boyle Engineering Corporation, whose address is 1600 WEST MAIN STREET, SUITE 1, LEESBURG, FLORIDA 34748, for Construction Management Services, Operation and Maintenance Manual Update, and Ground Water Monitoring Plan for upgrades to the Turnpike Water Reclamation Facility.
THAT this resolution shall become effective immediately.
PASSED AND ADOPTED by the City Commission of the City of Leesburg, Florida, at a regular meeting held the _____ day of _________ 2009.
__________________________
Mayor
ATTEST:
__________________________
City Clerk